Borik Residential Project. Installation of grounding [11.09.2024]
11. September 2024.Borik Residential Project. Construction Status Update [09.10.2024]
9. October 2024.Construction Status Update – Borik Residential Project
We are excited to report on the recent developments at the Borik Residential Complex. Construction continues to advance, with several significant milestones achieved:
- Reinforcement in the upper zone has been completed, ensuring structural stability.
- Special reinforcement against column penetration has been installed to provide additional support and durability to the structure.
- The elevator and pumping shafts have been successfully filled with concrete, marking a crucial step in the building's vertical infrastructure.
- Finally, the area below minus 1 floor has been filled with concrete, reinforcing the fundamental structure of the complex.